Subgrade work at #14 green complete and drainage pipe installed
according to plans.

Drainage pipe fittings and layout have been approved and the
next step is to cover pipe and trenches with gravel.

Plastic moisture barrier installed at perimeter of green.
4 inches of gravel then added to cover green subgrade.
Green now ready for greens mix or sand.

Earthwork continues on #5 fairway. Pond work to left of hole
complete. This hole will be similar to #4 at the Reserve Club.